Posted on: June 5, 2023
All local neighborhood traffic will be directed to take either Cloud Cap Ave from the south side or Mission Drive from the north side of construction with all traffic detouring to North Pagosa Boulevard.
Heavy trucks and trailers should bypass Pi...
Read on...
Road and Bridge Department
Posted on: June 1, 2023
Contractors have discovered a lack of existing asphalt on the road and will use additional material to complete the project. A change order was signed by the Board of County Commissioners and funds were allocated to produce a quality product.
Road and Bridge Department
Posted on: May 24, 2023
The repaving of Piedra Road (CR 600) has been postponed by the contractor to begin removing asphalt Tuesday June 6th. The project is expected to be complete by end of August. Expect delays and detours during this process.